Development intended 21 million to mount thee
Development intended 21 million to mount the drive via high-speed Caudete (Albacete), Alicante.
The Ministry of Development, through the Railway Infrastructure Administrator (ADIF) has awarded the joint venture formed by Dragados and Tecsa, the assembly work of the journey via Caudete (Albacete)-Alicante-of-66 km, with a budget of 21,153,597 euros, said today in a statement Prefectures.
The acting, for High Speed Line Madrid-Castilla La Mancha-Comunidad Valenciana-Region of Murcia, represents an important advance in the development of High Speed Line from Albacete to Alicante and, therefore, of the Madrid -Levante.
Via mounting begins with the collection of the sleepers, unloaded by trucks along the entire stretch. The track is included in the mounting bases for transport to the various points with trains lanes.
The assembly process via high-speed in several stages. Once downloaded the sleepers along the platform, extending a first layer of ballast-ballast-bed of 10 inches thick, on which the sleepers are placed 60 centimeters apart from each other.
The operations after the placement of the rail, concern the supply of ballast hoppers by train, batting track, stabilization, rail welding, release of tension and track profile.